Benefits Realisation Frameworks – A Useful Handle

One of the greatest challenges of project management is maintaining top-down support in the face of fluctuating priorities. If you elect to take on the role yourself and are peppered by other priorities, it can be a challenge to exactly remember why you are changing things and what your goals are. Sometimes you may not even notice you have reached your goal.

The Benefits Realisation Chart-room

The Benefits Realisation Model is a framework on which to hang key elements of any project. These traditionally include the following, although yours may not necessarily be the same:

  • Definition of the project goal
  • Quantification of intended benefits
  • Project plan versus actual progress
  • How you know you reached your goal
  • Quantification of actual benefits

Another way of describing Benefits Realisation Frameworks is they answer four fundamental questions that every project manager should know by heart:

  • What am I going to do?
  • How am I going to do it?
  • When will I know it’s done?
  • What exactly did I achieve?

The Benefits Realisation Promise

An astounding number of projects fail to reach completion, or miss their targets. It’s not for nothing that the expression ?after the project failed the non-participants were awarded medals? is often used in project rooms. We’re not saying that it is a panacea for success. However it can alert you to warnings that your project is beginning to falter in terms of delivering the over-arching benefits that justify the effort.

When Projects Wander Off-Target

Pinning blame on participants is pointless when project goals are flawed. For example, the goals may be entirely savings-focused and not follow through on what to do with the windfall. At other times realisation targets may be in place, but nobody appointed to recycle the benefits back into the organisation. This is why a Benefits Realisation Framework needs to look beyond the project manager?s role.

Realisation Management in Practice

If the project framework does not look beyond the project manager?s role, then it is over when it reaches its own targets ? and can even run the risk of being an event that feeds entirely off itself. In order to avoid a project being a means to its own end, this first phase must culminate with handover to a benefits realisation custodian.

An example of this might be a project to centralise facilities that is justified in terms of labour savings. The project manager?s job is to build the structure. Someone else needs to rationalise the organisation.

In conclusion, the Benefits Realisation Framework is a useful way of ensuring a project does not only achieve its internal goals, but also remains a focus of management attention because of its extended, tangible benefits.

Check our similar posts

Operational Efficiency Initiatives

When was the last time you checked your technology spending against your IT infrastructure’s contribution to the bottom line?

Chances are, what’s happening underneath all those automated processes, expensive hardware, and fancy graphical user interfaces is not doing your bottom line any good.

If you don’t keep a watchful eye, your IT operations can easily nurture a lot of wastage and unnecessary costs. Underutilised servers, duplicate processes, poorly managed bandwidths, and too much complexity are among the common culprits.

For minor problems, we can eliminate wastage by setting up some technology enhancements, instilling best practices, and performing a few tweaks. However, if you’re not adequately trained on how to go about with it, your band-aid solutions can add more complexity to the mix.

Of course, there will always come a time when you will have to spend on new technologies to maintain the overall efficiency of your IT infrastructure. Whether you intend to purchase new hardware or software applications or build an entirely new infrastructure, the sheer cost of such undertakings warrants seeking expert advice.

Failure to do so can result in fragmented resources lacking in cohesiveness, which don’t contribute to efficiency at all.

Our solutions for improving operational efficiencies cover the entire spectrum: from planning what to buy, optimising what you’ve already bought, to making your team comfortable with them all. Please find time to view our solutions below and uncover ways to drive those profits up even as you work within your budget.

 

More Operational Review Blogs

 

Carrying out an Operational Review

 

Operational Reviews

 

Operational Efficiency Initiatives

 

Operational Review Defined

 

FUJIFILM Cracks the Energy Code

FUJIFILM was in trouble at its Dayton, Tennessee plant in 2008 where it produced a variety of speciality chemicals for industrial use. Compressed-air breakdowns were having knock-on effects. The company decided it was time to measure what was happening and solve the problem. It hoped to improve reliability, cut down maintenance, and eliminate relying on nitrogen for back-up (unless the materials were flammable).

The company tentatively identified three root causes. These were (a) insufficient system knowledge within maintenance, (b) weak spare part supply chain, and (c) generic imbalances including overstated demand and underutilised supply. The maintenance manager asked the U.S. Department of Energy to assist with a comprehensive audit of the compressed air system.

The team began on the demand side by attaching flow meters to each of several compressors for five days. They noticed that – while the equipment was set to deliver 120 psi actual delivery was 75% of this or less. They found that demand was cyclical depending on the production phase. Most importantly, they determined that only one compressor would be necessary once they eliminated the leaks in the system and upgraded short-term storage capacity.

The project team formulated a three-stage plan. Their first step would be to increase storage capacity to accommodate peak demand; the second would be to fix the leaks, and the third to source a larger compressor and associated gear from a sister plant the parent company was phasing out. Viewed overall, this provided four specific goals.

  • Improve reliability with greater redundancy
  • Bring down system maintenance costs
  • Cut down plant energy consumption
  • Eliminate nitrogen as a fall-back resource

They reconfigured the equipment in terms of lowest practical maintenance cost, and moved the redundant compressors to stations where they could easily couple as back-ups. Then they implemented an online leak detection and repair program. Finally, they set the replacement compressor to 98 psi, after they determined this delivered the optimum balance between productivity and operating cost.

Since 2008, FUJIFILM has saved 1.2 million kilowatt hours of energy while virtually eliminating compressor system breakdowns. The single compressor is operating at relatively low pressure with attendant benefits to other equipment. It is worth noting that the key to the door was measuring compressed air flow at various points in the system.

ecoVaro specialises in analysing data like this on any energy type.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
The Connection Between Six Sigma and CRM

Six Sigma is an industrial business strategy directed at improving the quality of process outputs by eliminating errors and system variables. The end objective is to achieve a state where 99.99966% of events are likely to be defect free. This would yield a statistical rating of Sigma 6 hence the name.

The process itself is thankfully more user-friendly. It presents a model for evaluating and improving customer relationships based on data provided by an automated customer relations management (CRM) system. However in the nature of human interaction we doubt the 99.99966% is practically achievable.

Six Sigma Fundamentals

The basic tenets of the business doctrine and the features that set off are generally accepted to be the following:

  1. Continuous improvement is essential for success
  1. Business processes can be measured and improved
  1. Top down commitment is fundamental to sustained improvement
  1. Claims of progress must be quantifiable and yield financial benefits
  1. Management must lead with enthusiasm and passion
  1. Verifiable data is a non-negotiable (no guessing)

Steps Towards the Goal

The five basic steps in Six Sigma are define the system, measure key aspects, analyse the relevant data, improve the method, and control the process to sustain improvements. There are a number of variations to this DMAIC model, however it serves the purpose of this article. To create a bridge across to customer relationships management let us assume our CRM data has thrown out a report that average service times in our fast food chicken outlets are as follows.

<2 Minutes 3 to 8 Minutes 9 to 10 Minutes >10 Minutes
45% 30% 20% 5%
Table: Servicing Tickets in Chippy?s Chicken Caf?s

Using DMAIC to unravel the reasons behind this might proceed as follows

  • Define the system in order to understand the process. How are customers prioritised up front, and does the back of store follow suit?
  • Break the system up into manageable process chunks. How long should each take on average? Where are bottlenecks most likely to occur?
  • Analyse the ticket servicing data by store, by time of day, by time of week and by season. Does the type of food ordered have a bearing?
  • Examine all these variables carefully. Should there for example be separate queues for fast and slower orders, are there some recipes needing rejigging
  • Set a goal of 90% of tickets serviced within 8 minutes. Monitor progress carefully. Relate this to individual store profitability. Provide recognition.

Conclusion

A symbiotic relation between CRM and a process improvement system can provide a powerful vehicle for evidencing customer care and providing feedback through measurable results. Denizon has contributed to many strategically important systems.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?