Benefits Realisation Frameworks – A Useful Handle

One of the greatest challenges of project management is maintaining top-down support in the face of fluctuating priorities. If you elect to take on the role yourself and are peppered by other priorities, it can be a challenge to exactly remember why you are changing things and what your goals are. Sometimes you may not even notice you have reached your goal.

The Benefits Realisation Chart-room

The Benefits Realisation Model is a framework on which to hang key elements of any project. These traditionally include the following, although yours may not necessarily be the same:

  • Definition of the project goal
  • Quantification of intended benefits
  • Project plan versus actual progress
  • How you know you reached your goal
  • Quantification of actual benefits

Another way of describing Benefits Realisation Frameworks is they answer four fundamental questions that every project manager should know by heart:

  • What am I going to do?
  • How am I going to do it?
  • When will I know it’s done?
  • What exactly did I achieve?

The Benefits Realisation Promise

An astounding number of projects fail to reach completion, or miss their targets. It’s not for nothing that the expression ?after the project failed the non-participants were awarded medals? is often used in project rooms. We’re not saying that it is a panacea for success. However it can alert you to warnings that your project is beginning to falter in terms of delivering the over-arching benefits that justify the effort.

When Projects Wander Off-Target

Pinning blame on participants is pointless when project goals are flawed. For example, the goals may be entirely savings-focused and not follow through on what to do with the windfall. At other times realisation targets may be in place, but nobody appointed to recycle the benefits back into the organisation. This is why a Benefits Realisation Framework needs to look beyond the project manager?s role.

Realisation Management in Practice

If the project framework does not look beyond the project manager?s role, then it is over when it reaches its own targets ? and can even run the risk of being an event that feeds entirely off itself. In order to avoid a project being a means to its own end, this first phase must culminate with handover to a benefits realisation custodian.

An example of this might be a project to centralise facilities that is justified in terms of labour savings. The project manager?s job is to build the structure. Someone else needs to rationalise the organisation.

In conclusion, the Benefits Realisation Framework is a useful way of ensuring a project does not only achieve its internal goals, but also remains a focus of management attention because of its extended, tangible benefits.

Check our similar posts

Which KPI?s to Use in CRM

Customer relationship management emerged in the 1980?s in the form of database marketing. In those tranquil pre-social media days, the possibility of ?managing? clients may have been a possibility although Twitter and Facebook took care of that. Modern managers face a more dynamic environment. If you are one, then what are the trends you should be monitoring yourself (as opposed to leaving it to others).

If you want to drip feed plants, you have to keep the flow of liquid regular. The same applies to drip-feed marketing. Customers are fickle dare we say forgetful. Denizon recommends you monitor each department in terms of Relationship Freshness. When were the people on your list last contacted, and what ensued from this?

Next up comes the Quality of Engagements that follow from these efforts. How often do your leads respond at all, and how many interfaces does it take to coax them into a decision? You need to relate this to response blocks and unsubscribes. After a while you will recognise the tipping point where it is pointless to continue.

Response Times relate closely to this. If your marketing people are hot then they should get a fast response to sales calls, email shots and live chats. It is essential to get back to the lead again as soon as possible. You are not the only company your customers are speaking too. Fortune belongs to the fast and fearless.

The purpose of marketing is to achieve Conversions, not generate data for the sake of it. You are paying for these interactions and should be getting more than page views. You need to drill down by department on this one too. If one team is outperforming another consider investing in interactive training.

Finally Funnel Drop-Off Rate. Funnel analysis identifies the points at which fish fall off the hook and seeks to understand why this is happening. If people click your links, make enquiries and then drift away, you have a different set of issues as opposed to if they do not respond at all.

You should be able to pull most of this information off your CRM system if it is half-decent, although you may need to trigger a few options and re orientate reporting by your people in the field. When you have your big data lined up speak to us. We have a range of data analysts brimming over with fresh ideas.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Green Business!

Carbon emissions reduction has evolved beyond simply good citizenship to being a business tool. Implementing ?green? initiatives is now a competitive weapon which defines real business opportunities and bottom line savings that can contribute significant financial value to the organisation while meeting demanding customer requirements for sustainable and low-carbon products.

Energy efficiency is a low cost resource for achieving carbon emissions reduction. Better energy efficiency simply translates to lesser carbon emissions and less energy usage which translates into saved costs.

Reduction of an organisations carbon footprint is each and everyone?s responsibility. Human activities are the key responsibility for the release of greenhouse gas emissions into the atmosphere. These include usage of electricity generated from fossil fuel, heating or driving.

At the corporate level, various measures can be instigated to increase energy efficiency. Some of these can be, having zone lighting with sensors to minimise unnecessary office lighting, timers on large IT equipment, promoting energy efficient behaviour in the office, asking staff to switch off and unplug appliances when not in use and minimising staff travel.
At the individual level; it is the small habits that count; cultivating the habit of switching off unnecessary lights, plugging out appliances that are not in use, using video conferencing or online chatting instead of having to travel to meetings, using public transport instead of taking a taxi/ personal car and using energy efficient cars.

All these initiatives assist organisations in their corporate social responsibility reports and play a role in sustainability rankings which is instrumental to customers who are increasingly considering sustainability rankings in investment decisions, while achieving the goal of cost reduction internally.

Ready to work with Denizon?