ESOS Guide for UK Manufacturers Available

The Engineering Employers’ Federation (EEF) is the UK’s largest sectoral structure. Its goal is to promote the interests of manufacturing, engineering and technology-based businesses in order to enhance their competitiveness.

EEF has positioned itself in London and Brussels in order to be in a position to lobby at EU and Westminster level. Part of its role is helping its members adapt to change and capitalise on it. When it discovered that a third of UK manufacturers must comply with ESOS (and 49% had not even heard of it) EEF decided it was time to publish a handbook for its members.

According to EEF’s head of climate and environment policy Gareth Stace, For the many manufacturers that have already taken significant steps to improve energy efficiency, ESOS can be viewed as a ?stock taking exercise?, ensuring that momentum is maintained and new measures are highlighted and taken when possible?.

He goes on to add that others that have not begun the process should view it as an ‘impetus’ to go head down and find the most cost-effective ways to slash energy costs. Ecovaro adds that they would also have the opportunity to reduce carbon emissions almost as a by-product.

Firms with more than 250 employees, over 250 million revenue or both must comply with ESOS across all UK sectors. In simplest terms, they must have conducted an energy audit by 5th December 2015, and logged their energy saving plan with the Environmental Agency that is Britain?s sustainability watchdog.

The Department of Energy & Climate Change (DEEC) that oversees it believes that large UK businesses are wasting ?2.8 billion a year on electricity they do not need. Clearly it makes sense to focus on larger targets; however EcoVaro believes those halfway to the threshold should voluntarily comply if cutting their energy bills by 25% sounds appealing.

We are able to assist with interpreting their energy audits. These are often a matter of installing sub-meters at distribution points, and reading these for a few representative months to establish a trend. Meters are inexpensive compared to electricity costs, and maintenance teams can install them during maintenance shutdowns.

Ecovaro helps these firms process the data into manageable summaries using cloud-based technology. This is on a pay-when-used basis, and hence considerably cheaper than acquiring the software, or appointing a consultant.

Check our similar posts

Excel Spreadsheet Conversion to SQL Reports

Spreadsheets are flexible, inexpensive and easy to use. They are especially handy when it comes to beating report submission deadlines or making impromptu data computations.

Unfortunately, organisations heavy reliance on spreadsheets have made these User Developed Applications (UDA) into high-risk office tools. Simple spreadsheet errors like leaving out a negative sign or a cut-and-paste mistake have already caused million-dollar discrepancies. Also, when a fraudulent employee enters into the picture, the risks become unimaginable.
Think TransAlta’s spreadsheet cut-and-paste glitch (the company later called this a ‘simple clerical error’) which caused the energy firm a whopping $24 million loss or Fidelity’s overstatement of its earnings owing to the omission of the minus sign on the spreadsheet of a $1.3 billion net capital loss.

Denizon can convert your Excel Spreadsheets to a web based SQL Server Reporting Services (SSRS). It does not import Excel data, rather it allows the creation and deployment of reports in a more efficient manner by querying the data.

So what is the problem with Spreadsheets?

  • Plagued with risk issues and vulnerable to fraud
  • Lacking in control features especially when copied, edited and emailed between many users
  • A burden to regulation compliance e.g. SOX (Sarbanes-Oxley)
Moreover:
  • Accidental copy-paste/Omission of a negative sign/Erroneous range selection
  • Incorrect data input or unintentional deletion of a character, cell, range, column, or row
  • Possibility of the user working on the wrong version
  • Prone to inconsistent company-wide reporting
  • Often ‘defenceless’ against unauthorised access

See Top 10 Disadvantages of Spreadsheets

What makes SQL Server Reporting Services better than Spreadsheets?

  • Free from spreadsheet risks & equipped with built-in controls that substantially reduce risks to data
  • Less prone to fraud
  • More suitable for regulatory compliance e.g. SOX
  • Designed for an agile business environment

Automatic consolidation eliminates errors and wasted time caused by tedious copy-pasting of data and linking of cells
Better collaboration capabilities allows team members to bring their heads together for planning, budgeting, and reporting even while on the go
Mobility support enables users to input data or retrieve information through their wireless mobile device

Superior sharing features ensures that everyone is exactly on the same page and viewing real-time information
Dashboards provide insightful information at-a-glance through KPIs, graphs, and various metrics
Drill-downs enable users to investigate unusual figures and gain a better understanding of the details that contribute to the big picture
Easy to learn interfaces allow your organisation to cope with fast personnel turnaround or Mergers & Acquisitions

Don’t know how to shift from Spreadsheets to SQL Server Reporting Services?

We’ve got the knowledge and expertise to assist you in:

  • Making a smooth and cost-efficient transition from risky spreadsheets to reliable reports
  • Designing and implementing SOX-compliant report-generating methods and procedures
  • Putting exposure to high-risk reporting methods a thing of the past
Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

2015 ESOS Guidelines Chapter 7, 8 & 9 – Sign-Off, Compliance & Appeals

This is the final chapter in our series of short posts summarising the quite complex ESOS guidelines (click on ?Comply with ESOS? to see the details). This one addresses the legalities to follow to complete your report – and how to appeal if you are not happy with any of the Environment Agency?s decisions.

  1. Director Sign-Off

This is by no means an easy ride. Confirmation of the work at individual or lead assessor level locks the company into the penalty cycle in the event there are significant irregularities. By signing off the assessment, the board level director(s) # agree that they have

  • Reviewed the enterprise?s ESOS recommendations
  • Believe the enterprise is within the scope of the scheme
  • Believe the enterprise is compliant with the scheme
  • Believe the information provided is correct

Having an internal assessor requires a second board-level signature.

  1. Compliance

You report compliance on the internet. This is free and you can do it at any time within the deadline. You can dip in and out of the process as many times as you wish, but must use the link in the receipting email. While this is something a board member must do, there is no reason why the lead assessor should not complete the basics. The online compliance notification addresses the following topics:

  • The ESOS contact person in the enterprise
  • Any aggregation / dis-aggregation during the period
  • The names and contact details of the lead assessor
  • The proportion of energy consumption per compliance route

The Environment Agency will acknowledge receipt. This does not constitute acceptance. You should keep the ESOS evidence pack in a safe place with at least one backup elsewhere.

  1. Compliance & Enforcement Issues

In the event the Environment Agency decides your enterprise has not met ESOS requirements, it may either (a) issue a compliance notice with instructions, or (b) apply one of the following civil penalties:

  • A fine of up to ?5,000 for failure to maintain records
  • A fine of up to ?50,000 for failure to undertake an energy audit
  • A fine of up to ?50,000 for a false or misleading statement

Any enterprise has the right of appeal against government decisions. In the case of ESOS, this is via:

  • The First-Tier Tribunal if your enterprise is England, Wales or off-shore based
  • The Scottish Minister if your enterprise is based in Scotland
  • The Planning Commission if your enterprise is Northern Ireland-based

The notice you appeal against will supply details of the appeal steps to take.

This blog and its companion chapters concerning the ESOS Guidelines as amended 2015 are with compliments of ecoVaro. We are the people who break ESOS data into manageable chunks of information, so that board-level directors have greater confidence in what they sign.

Ready to work with Denizon?