Scrumming Down to Complete Projects

Everybody knows about rugby union scrums. For our purposes, perhaps it is best to view them as mini projects where the goal is to get the ball back to the fly-half no matter what the opposition does. Some scrums are set pieces where players follow planned manoeuvres. Loose / rolling scrums develop on the fly where the team responds as best according to the situation. If that sounds to you like software project management then read on, because there are more similarities?.

Isn’t Scrum Project Management the Same as Agile?

No it’s not, because Scrum is disinterested in customer liaison or project planning, although the team members may be happy to receive the accolades following success. In the same way that rugby players let somebody else decide the rules and arrange the fixtures, a software Scrum team just wants the action.

Scrum does however align closely ? dare I say interchangeably with Agile?s sprints. Stripping it of all the other stages frees the observer up to analyse it more closely in the context of a rough and tumble project, where every morning can begin with a backlog of revised requirements to back fit.

The 3 Main Phases of a Scrum

A Scrum is a single day in the life of a project, building onto what went before and setting the stage for what will happen the following day. The desired output is a block of component software that can be tested separately and inserted later. Scrumming is also a useful technique for managing any project that can be broken into discreet phases. The construction industry is a good example.

Phase 1 – Define the Backlog. A Scrum Team?s day begins with a 15 minute planning meeting where team members agree individual to-do lists called ?backlogs?.

Phase 2 – Sprint Towards the Goal. The team separates to allow each member to complete their individual lines of code. Little or no discussion is needed as this stage.

Phase 3 – Review Meeting. At the end of each working day, the team reconvenes to walk down what has been achieved, and check the interconnected functionality.

The 3 Main Phases of a Scrum ? Conclusions and Thoughts

Scrum is a great way to liberate a competent project team from unnecessary constraints that liberate creativity. The question you need to ask yourself as manager is, are you comfortable enough to watch proceedings from the side lines without rushing onto the field to grab the ball.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Check our similar posts

Key Steps to Complying with ESOS

Energy Savings Opportunity Scheme has already been launched. In fact, it is by now in its initial phase. However, many businesses are still not aware of the new scheme, especially those who are covered by the qualifications for ESOS. To help them understand what they need to do in compliance to the energy efficiency strategy, here are key steps they can follow along the way.

Measure Overall Energy Consumption

The first step to complying with ESOS is to make an initial estimate of the business? energy consumption. This includes measuring the use of electricity, renewable energy, combustible fuels and all other forms of energy consumed whether in buildings, transports and industrial processes.

Three important factors to consider are the measurement units used, the reference period and quality of data. Energy units, such as MWh and GJ, or energy expenditure costs should be applied. Business enterprises should also do the initial measurement within a reference period of 12 months. Moreover, data collected should be verifiable at hand.

Identify Areas of Significant Energy Consumption

When the total energy consumption for all the activities and assets has already been estimated, it’s then time to identify what areas in the organisation comprise the significant portion of the overall energy usage. The areas recognised should cover at least 90% of the overall consumption. Meaning to say, ESOS participants have the chance to omit 10% of the energy consumption and instead focus on the 90%. This would ensure that subsequent energy audits will be cost-effective and proportionate.

Consider and Choose Compliance Routes

In order to comply with ESOS, qualified businesses should consider what compliance routes to take. These routes include taking series of energy audits, operating and implementing a certified ISO 50001 energy management system, acquiring Display Energy Certificates (DECs) and working with Green Deal assessments. Whichever route the business takes, one should maintain credible evidences, along with helpful documents, to certify their compliance.

Report the Compliance

Except when the large enterprise covers all the significant areas of energy consumption by means of ISO 50001 certification, one should appoint a lead assessor to supervise, conduct and review the organisation’s chosen ESOS compliance route. In this case, the approved assessments should then be signed off at board level to ensure that the conclusions and recommendations for energy savings are properly carried. To confirm their compliance, the business should submit a formal notification to the Environment Agency.

Because ESOS is not just an opportunity but also an obligation, it designated compliance bodies and gave them the authority to file civil penalties towards those who fail to comply with the scheme. Not only that, these appropriate authorities have the right to publish information about non-compliant enterprises including their name, details of non-compliance and corresponding penalty amount. Among these UK compliance bodies are Natural Resources Wales, Environment Agency in England, The Scottish Environment Protection Agency (SEPA) and Northern Ireland Environment Agency.

So, if you are covered with the ESOS qualifications, make sure to be informed. As the famous saying goes, ?Ignorance of the law excuses no one.? Likewise, awareness of ESOS is a responsibility every large business in UK should give importance to.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Making Click-and-Collect click

In my previous post, I introduced you to integrated e-commerce and explained why it is the right way to extend your business online. If you already have a brick-and-mortar retailing business and you’re looking to improve your online presence, you could start offering a click-and-collect service.

With click-and-collect, customers order online and then collect their merchandise from one of the retailer?s local branches. Why would they want to do that?

Apparently, there are buyers who now prefer a click-and-collect service over the delivery service of a purely online retailer. With the latter, they sometimes have to wait forever for the delivery van to arrive or contend with a missed-delivery card.

Basically, customers who want both the convenience of placing orders online and better control of their time find click-and-collect a better option.

Last December 2011, IMRG (Interactive Media in Retail Group) reported a ?significant rise in the percentage of click-and-collect e-retail sales in the 3rd quarter of 2011?. This accounted for 10.4% of all e-retail sales in that quarter. More specifically, the gain was 7.4%, which was also the strongest quarterly gain since IMRG started collecting this data.

Clearly, this particular service is gaining popularity. But how do you meet the rising demand in this area?

A click-and-collect service requires a highly synchronised ecosystem. You don’t want to have a customer order items from your online store, drive a couple of minutes from his house to your nearest outlet, only to find out that one of the items is no longer available.

This can only work if all systems involved are interconnected. Changes in the inventory in your individual outlets should reflect on your database in real time. In turn, these changes have to be reflected instantly on your online store. Conversely, once a buyer has picked items online and is already directed to a local outlet, those items have to be reserved there.

But that’s not all. Your system has to be seamless enough to support fast and reliable service. You don’t want your buyer to have to wait a long time before the items are ready for pick-up. It also has to be capable of tracking the status of ordered products, handling uncollected orders, and monitoring inventory.

By implementing an integrated e-commerce system, these won’t be the only things you?d be able to do. You can even add more value to your service. For example, you can connect to your CRM and learn more about your customers? purchase history, buying habits, and preferences.

That way, it would be easier for you to provide a faster and more convenient buying experience for them in the future.

Click-and-collect is a very promising way to increase your sales and improve customer loyalty.

Ready to work with Denizon?