What Energy Management Software did for CDC

Chrome Deposit Corporation ? that’s CDC for short ? reconditions giant rollers used to finish steel and aluminium sheets in Portage, Indiana by applying grinding, texturing and plating methods. While management was initially surprised when the University of Delaware singled their plant out for energy assessment, this took them on a journey to bring energy consumption down despite being in an expansion phase.

Metal finishing and refinishing is an energy-intensive business where machines mainly do the work while workforces as small as 50 individuals tend them. Environmental impacts also need countering within a challenging environment of burgeoning natural gas and electricity prices.

The Consultant’s Recommendations

The University of Delaware was fortunate that Chrome Deposit Corporation had consistently measured its energy consumption since inception in 1986. This enabled it to pinpoint six strategies as having potential for technological and process improvements.

  • Insulate condensate tanks and pipes
  • Analyse flue gas air-fuel ratios
  • Lower compressed air pressures
  • Install stack dampers on boilers
  • Replace belts with pulleys and cogs
  • Fit covers on plant exhaust fans

CDC implemented only four of the six recommendations. This was because the boiler manufacturer did not recommend stack dampers, and the company was unable to afford certain process automation and controls.

Natural Gas Savings

The project team began by analysing stack gases from boilers used to heat chrome tanks and evaporate wastewater. They found the boilers were burning rich and that several joints in gas lines were leaking. Correcting these issues achieved an instant gas saving of 12% despite increased production.

Reduced Water Consumption

The team established that city water was used to cool the rectifiers. It reduced this by an astonishing 85% by implementing a closed-loop system and adding two chillers. This also helped the water company spend less on chemicals, and energy to drive pumps, purifiers and fans.

Summary of Benefits

Electricity consumption reduced by 18% in real terms, and natural gas by 35%. When these two savings are merged they represent an overall 25% energy saving. These benefits were implemented across the company?s six other plants, resulting in benefits CDC management never dreamed of when the University of Delaware approached them.

ecoVaro offers a similar data analytics service that is available online worldwide. We have helped other companies slash their energy bills with similarly exciting results. We?ll be delighted to share ideas that only data analytics can reveal.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Check our similar posts

Top 3 reasons to get into Multi-Channel Retail

Multi-channel retail, which nowadays understandably includes online channels, is something you just have to do this year. Every single day you put off doing it, the competition gobbles up market share that should have been yours. There are a number of reasons why even successful retailers are now going into multi-channel retailing. Here?s three of the most important ones.

1. You’ll get a BIG jump in sales

Not counting this year, which could be getting a big boost from major activities like the Queen?s Diamond Jubilee and the 2012 Olympics, sales of UK retailers have been experiencing tremendous growth particularly from their online channels. Already two years ago (2010), a number of UK retailers boasted significant increases in sales as a result of multi-channel retail initiatives. These retailers included:

  • Argos, which got a whopping ?1.9bn from multichannel sales back then;
  • House of Fraser, which reported a 150% jump in its online sales in just 6 months; and
  • Debenhams, whose profits rose by 20%

There were many others. Now, the reason I?m showing you 2010 figures is because online retail sales increased by 14% in 2011 and those same businesses still added to that growth. So, if only you had enough foresight and started expanding your business to the Web two years ago, you could just imagine what your sales would have been today.

The good news is that, it’s not yet too late if you start now. Here?s why…

2. Those numbers are going to keep on growing

We’re getting all sorts of predictions from leading researchers regarding the possible growth of the Internet economy. All these predictions have one thing in common. They all have a positive outlook. The Boston Consulting Group (BCG), for instance, predicts an average growth of no less than 10% per year in the G-20 nations.

3. Most online retailers aren’t doing it right yet

Although many retailers have already started bringing their business to the Web, most of them are doing it the wrong way. For example, many of them fail to integrate their offline and online channels. This is a serious shortcoming because it leads to customer dissatisfaction.

When a customer goes to your website and sees something he likes, you wouldn’t want him to drive all the way to your store only to find out that the item isn’t available there or, if the item is there, that it isn’t priced as he expected. The lack of multi-channel integration is very common among multi-channel retailers.

These inadequacies are actually good news because it means there are still many areas you can improve on. After improving on them, you can then highlight those areas as your key differentiators.

If you’re still looking for more reasons on why you should go into multi-channel retailing, read this post:

5 Numbers Showing Why the Time to Invest on eCommerce in the UK is Now

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
FUJIFILM Cracks the Energy Code

FUJIFILM was in trouble at its Dayton, Tennessee plant in 2008 where it produced a variety of speciality chemicals for industrial use. Compressed-air breakdowns were having knock-on effects. The company decided it was time to measure what was happening and solve the problem. It hoped to improve reliability, cut down maintenance, and eliminate relying on nitrogen for back-up (unless the materials were flammable).

The company tentatively identified three root causes. These were (a) insufficient system knowledge within maintenance, (b) weak spare part supply chain, and (c) generic imbalances including overstated demand and underutilised supply. The maintenance manager asked the U.S. Department of Energy to assist with a comprehensive audit of the compressed air system.

The team began on the demand side by attaching flow meters to each of several compressors for five days. They noticed that – while the equipment was set to deliver 120 psi actual delivery was 75% of this or less. They found that demand was cyclical depending on the production phase. Most importantly, they determined that only one compressor would be necessary once they eliminated the leaks in the system and upgraded short-term storage capacity.

The project team formulated a three-stage plan. Their first step would be to increase storage capacity to accommodate peak demand; the second would be to fix the leaks, and the third to source a larger compressor and associated gear from a sister plant the parent company was phasing out. Viewed overall, this provided four specific goals.

  • Improve reliability with greater redundancy
  • Bring down system maintenance costs
  • Cut down plant energy consumption
  • Eliminate nitrogen as a fall-back resource

They reconfigured the equipment in terms of lowest practical maintenance cost, and moved the redundant compressors to stations where they could easily couple as back-ups. Then they implemented an online leak detection and repair program. Finally, they set the replacement compressor to 98 psi, after they determined this delivered the optimum balance between productivity and operating cost.

Since 2008, FUJIFILM has saved 1.2 million kilowatt hours of energy while virtually eliminating compressor system breakdowns. The single compressor is operating at relatively low pressure with attendant benefits to other equipment. It is worth noting that the key to the door was measuring compressed air flow at various points in the system.

ecoVaro specialises in analysing data like this on any energy type.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Using Pull Systems to Optimise Work Flows in Call Centres

When call centres emerged towards the end of the 20th century, they deserved their name ?the sweatshops of the nineties?. A new brand of low-paid workers crammed into tiny cubicles to interact with consumers who were still trying to understand the system. Supervisors followed ?scientific management? principles aimed at maximising call-agent activity. When there was sudden surge in incoming calls, systems and customer care fell over.

The flow is nowadays in the opposite direction. Systems borrowed from manufacturing like Kanban, Pull, and Levelling are in place enabling a more customer-oriented approach. In this short article, our focus is on Pull Systems. We discuss what are they, and how they can make modern call centres even better for both sets of stakeholders.

Pull Systems from a Manufacturing Perspective

Manufacturing has traditionally been push-based. Sums are done, demand predicted, raw materials ordered and the machines turned on. Manufacturers send out representatives to obtain orders and push out stock. If the sums turn out wrong inventories rise, and stock holding costs increase. The consumer is on the receiving end again and the accountant is irritable all day long.

Just-in-time thinking has evolved a pull-based approach to manufacturing. This limits inventories to anticipated demand in the time it takes to manufacture more, plus a cushion as a trigger. When the cushion is gone, demand-pull spurs the factory into action. This approach brings us closer to only making what we can sell. The consumer benefits from a lower price and the accountant smiles again.

Are Pull Systems Possible in Dual Call Centres

There are many comments in the public domain regarding the practicality of using lean pull systems to regulate call centre workflow. Critics point to the practical impossibility of limiting the number of incoming callers. They believe a call centre must answer all inbound calls within a target period, or lose its clients to the competition.

In this world-view customers are often the losers. At peak times, operators can seem keen to shrug them off with canned answers. When things are quiet, they languidly explain things to keep their occupancy levels high. But this is not the end of the discussion, because modern call centres do more than just take inbound calls.

Using the Pull System Approach in Dual Call Centres

Most call centre support-desks originally focused are handling technical queries on behalf of a number of clients. When these clients? customers called in, their staff used operator?s guides to help them answer specific queries. Financial models?determined staffing levels and the number of ?man-hours? available daily. Using a manufacturing analogy, they used a push-approach to decide the amount of effort they were going to put out, and that is where they planted their standard.

Since these early 1990 days, advanced telephony on the internet has empowered call centres to provide additional remote services in any country with these networks. They have added sales and marketing to their business models, and increased their revenue through commissions. They have control over activity levels in this part of their business. They have the power to decide how many calls they are going to make, and within reason when they are going to make them.

This dichotomy of being passive regarding incoming traffic on the one hand, and having active control over outgoing calls on the other, opens up the possibility of a partly pull-based lean approach to call centre operation. In this model, a switching mechanism moves dual trained operators between call centre duties and marketing activities, as required by the volume of call centre traffic, thus making a pull system viable in dual call centres.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?