Data Replication

Medical Data Form

These days, not many companies can continue to operate once their entire computer system goes down. All the information needed in daily operations are stored in databases while the interfaces that make use of them all come in the form of software applications.

Software applications can be rapidly reinstalled and configured for as long as the necessary programs are available. Data, however, cannot be reconstructed as quickly even with hard copies available. It is therefore necessary to store your data in a replicated setup so that when one section goes down, operations can proceed without interruption.

For instance, if a category 5 hurricane renders your main office useless, you can simply rent workstations elsewhere, connect to the Internet and continue with your usual transactions for as long as data is readily accessible.

So how do we ensure the accessibility and reliability of your data? Here’s what we’ll do:

  • Activate data replication on your database management system. If your DBMS does not support replication, we’ll migrate all your data to one that does.
  • If absolutely necessary, we can allow modernised systems to run parallel to your legacy systems and prepare both for full modernisation when you’re ready.
  • Implement fail-over technologies where applicable to provide for automatic switching to a backup data server or network from one that has just failed.

We can also assist you with the following:

Check our similar posts

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Energy Savings Opportunity Scheme (ESOS): An Overview

Energy management is crucial to most businesses in the UK. This is primarily because energy usage substantially affects all organizations, whether large or small. The good news is that, energy costs can be controlled through improved energy efficiency. And this is exactly why Energy Savings Opportunity Scheme (ESOS) came into being ? to promote competitiveness among businesses.

Energy Savings Opportunity Scheme is the realisation of the UK Government’s ambition towards achieving the maximum potential of cost-effective energy in the economy. ESOS aims to stimulate innovation and growth, cut emissions and support a sustainable energy system.

ESOS at a Glance – Legal Perspective

The EU Energy Efficiency Directive took a major step forward on November 14, 2012 and headed towards establishing a framework to promote energy efficiency across various economic sectors. To interpret Article 8 of the Directive, the government has given birth to ESOS; requiring large enterprises to undergo mandatory energy audits and energy management systems by December 5, 2015 and at least every 4 years thereafter.

Large enterprises include UK companies that have more than 250 employees or those businesses whose annual turnover exceeds ?50 million and whose statement of financial position totals more than ?43 million. With this, over 7000 of the biggest companies in Britain will need to comply with ESOS as an approach to review their total energy use in buildings, business operations, transport and industrial processes.

Generally, ESOS is both an obligation and an opportunity. It is an obligation for the indicated target companies since they need to submit to additional regimes; focus on audit evidences; act in accordance to group structures and compliance; and observe limited penalties and note retention periods. Moreover, it is also an opportunity for companies to strive for more savings on energy projects; attempt to standardise their potential market; and effectively lower debt and legal costs.

ESOS Audits ? Looking Beyond

According to the Department of Energy and Climate Change (DECC), average first audit costs would be estimated at about ?17,000 and subsequent ones at around ?10,000. As expected, these audits will result in energy saving recommendations, of which companies need not proceed for a follow up; and substantially improve businesses in their energy management issues. DECC further states that every business that complies with ESOS could save an average of ?56,400 each year from an initial investment of ?17,000 only.

Currently, up to 6,000 UK businesses are already subject to existing CRC Carbon Reduction Scheme, Mandatory Carbon Reporting, Climate Change Levy and other compliance. This signifies that ESOS may overlap with prevailing energy efficiency legislation and may put additional pressure on energy administration. While this is true, however, ESOS holds extensive benefits. Although the scheme can be viewed as another costly compliance to environmental standards, ESOS goes straight to the bottom line and provides the organisation with competitive advantage. If large businesses act now and comply with it, they will be able to enjoy maximised payback in the long run.

Indeed, Energy Savings Opportunity Scheme is already here. It is mandatory with minimal investment. And all you have to do is act quickly, implement new improvements and earn more.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
How Volvo Dublin achieved Zero Landfill Status

The sprawling New River Valley Volvo plant in Dublin, Virginia slashed its electricity bill by 25% in a single year when it set its mind to this in 2009. It went on to become the first carbon-neutral factory in 2012 after replacing fossil energy with renewable power. Further efforts rewarded it with zero-landfill status in 2013. ecoVaro decided to investigate how it achieved this latest success.

Volvo Dublin?s anti-landfill project began when it identified, measured and evaluated all liquid and solid waste sources within the plant (i.e. before these left the works). This quantified data provided its environmental project team with a base from which to explore options for reusing, recycling and composting the discards.

Several decisions followed immediately. Volvo instructed its component suppliers to stop using cardboard boxes and foam rubber / Styrofoam as packaging, in favour of reusable shipping containers. This represented a collaborative saving that benefited both parties although this was just a forerunner of what followed.

Next, Volvo?s New River Valley truck assembly plant turned its attention to the paint shop. It developed methods to trap, reconstitute and reuse solvents that flushed paint lines, and recycle paint sludge to fire a cement kiln. The plant cafeteria did not escape attention either. The environment team made sure that all utensils, cups, containers and food waste generated were compostable at a facility on site.

The results of these simple, and in hindsight obvious decisions were remarkable. Every year since then Volvo has generated energy savings equivalent to 9,348 oil barrels or if you prefer 14,509 megawatts of electricity. Just imagine the benefits if every manufacturing facility did something similar everywhere around the world.

By 2012, the New River Valley Volvo Plant became the first U.S. facility to receive ISO 50001 energy-management status under a government-administered process. Further technology enhancements followed. These included solar hot water boilers and infrared heating throughout the 1.6 million square foot (148,644 square meter) plant, building automation systems that kept energy costs down, and listening to employees who were brim-full with good ideas.

The Volvo experience is by no means unique although it may have been ahead of the curve. General Motors has more than 106 landfill-free installations and Ford plans to reduce waste per vehicle by 40% between 2010 and 2016. These projects all began by measuring energy footprints throughout the process. ecoVaro provides a facility for you to do this too.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?